ROANOKE, VA –Adams Construction Company will continue milling and paving operations the week of April 8. The following streets are included in the paving list for this week:
- Masons Mill Road NE
- Manning Road NE
- 20th Street NE
- Templeton Avenue NE
- Plantation Ave NE from Orange Ave to Liberty Rd
And the following neighborhood streets:
Roundhill Neighborhood | Mecca Gardens Neighborhood |
- Herbert St
- Durham St
- Edinburg Dr
- Churchill Dr
- Cornell Dr
- Vancouver Dr
- Dorchester Dr
- Pawling St
- Daleville St
- Floraland Dr
| - Meadowrun Rd
- Springtree Rd
|
Milling operations will precede paving. Traffic control will direct traffic around the various projects areas. Adjacent streets may be impacted with traffic delays. No detours will be established. Please use caution when traveling these locations.
Contact Person:
- Keith Myers, Adams Construction, 540-982-2366